In February 2023, 10X Solar Power successfully commissioned a 2 MW ground-mounted solar power plant for Atri Glare Solar Pvt. Ltd. in Jagsa, Budiwada, Blotra – Rajasthan, under the PM-KUSUM Component-A scheme. This fixed-structure solar plant was completed in a record 45 days, showcasing our strength in rapid deployment without compromising on engineering quality and compliance.

The project, spearheaded by client Mr. Yatendra Atri, demonstrates our end-to-end EPC capabilities—including land assessment, DPR preparation, civil and electrical execution, and grid synchronization. Our team also managed the entire project financing process through the State Bank of India (SBI), including document submission, loan coordination, and disbursement support—ensuring smooth financial closure with zero delays.

Engineering Precision with Financial Simplicity

This fixed-tilt installation was designed for long-term reliability, minimal maintenance, and optimal energy yield. The site in Jagsa offered excellent solar irradiance, and the project was optimized with a robust structure capable of handling wind loads and harsh weather. Despite site and logistics constraints, the plant was fully tested, certified, and commissioned well within the project deadline.

 

Every component—solar modules, mounting structures, inverters, and safety systems—was chosen to meet MNRE and DISCOM standards. The smooth DISCOM approvals, successful SBI financing, and flawless commissioning within just 45 days made this project a showcase of our efficiency and execution excellence under the PM-KUSUM scheme.

project-003
blog2
project-002

 

“I am highly impressed by the commitment and speed of the 10X Solar Power team. From planning and approvals to financial documentation and final commissioning, their team handled every step professionally. Completing a 2 MW plant in just 45 days was beyond our expectations. I fully recommend them for ground-mounted solar projects.”

Yatendra Atri, Director, Atri Glare Solar Pvt. Ltd.

AMC Services Provided

A full Annual Maintenance Contract (AMC) was signed post-commissioning. Our team performs regular site inspections, module cleaning, system diagnostics, and preventive maintenance to ensure the plant maintains high performance year-round.

Conclusion

 

The Atri Glare Solar 2 MW project is a shining example of speed, quality, and execution strength. With end-to-end EPC, complete financing via SBI, and full compliance with PM-KUSUM Component-A, 10X Solar Power delivered a high-efficiency solar plant that meets the future energy needs of Rajasthan. We continue to empower clients with turnkey solar solutions backed by experience and integrity.

1

Rapid Execution

Completed within just 45 days—fastest in its category under PM-KUSUM.

2

Fixed Structure Design

Cost-effective, durable, and low-maintenance system for long-term output.

3

SBI Financing

Complete loan and financial documentation handled by 10X Solar Power.

4

Strategic Location

Located in Jagsa, Blotra (Rajasthan), with optimal land and sunlight availability.